Hello!Just wanted to see if I can get an idea on what caused the recent delay with the 94134 area. Was excited when it moved into construction phase a few months ago, after waiting 2 years of coming soon. Actually saw sonic trucks around doing work on the poles.
The estimated golive date has been slowly pushing out a month or 2 every month, which recently moved to Sept and Oct 2024 (different parts of 94134) for most of July. Then it suddenly jumped to Dec/Jan 2025 last week, then a couple days later its at Apr/June 2025.
Just curious to see what may be causing the big jump in delay.
It seems we are waiting for ADA ramp permits before being able to move forward. Hopefully, we are able to get these permits quickly.
Best Wishes!
Statistics: Posted by jerrielm — Mon Aug 12, 2024 10:00 am